Brampton-Caledon Airport Improvements ~ Sept 17 to Nov 30, 2018

The following information was updated on November 21st, 2018

The NOTAM’s are still in effect for Alpha and the main apron as follows:

180288 CYBM BRAMPTON-CALEDON
CNC3 TWY A AVBL ONLY TO ACFT WITH GEAR WID 3 METRES OR LESS
1810291245 TIL 1811301600
180289 CYBM BRAMPTON-CALEDON
CNC3 APN CLSD DUE CONST
1810291249 TIL 1811301600

Most of the construction has now been completed with the exception of the retaining wall by Hangar 3 and the asphalt. The weather for November has been colder than usual, along with the snow. We now have a very small window of opportunity to put the asphalt down.

PLEASE BE ADVISED THAT SUNDAY, NOVEMBER 25, 2018 MAY BE THE DAY THAT THE FINAL LAYER OF ASPHALT WILL BE PUT DOWN ON ALPHA TAXIWAY AND THE MAIN RAMP. IF THAT HAPPENS, THERE MAY BE DELAYS FOR AIRCRAFT USING THE AIRPORT AND THERE MAY BE A PERIOD OF TIME THAT THE RUNWAYS WILL BE CLOSED AS THE PAVERS MOVE OVER RUNWAY 33. A NOTAM will be issued as soon as the decision is made and it is totally dependent on weather.

It is still anticipated that the construction work will be completed by the end of November.

The following is an overview of the work that is being done. Updates will follow, as they are confirmed.

Pilots and Airport Users. Please also refer to SPECIAL PROCEDURES & SAFETY

BRAMPTON FLYING CLUB APRON AND ALPHA TAXIWAY REHABILITATION

Phase 1 & 2 ~ Alpha Taxiway

Stage one has been completed. The taxiway is useable but the sides need soil and grading and a final layer of asphalt is still required on Alpha taxiway.

Phase 3 ~ Access Road Limit of Construction

Completed.

Phase 4 ~ Pavement Restoration Adjacent to Hangars

The work schedule for this phase has been changed.

This will be the general direction for aircraft to taxi to the fuel pumps.

Phase 5, 6, and 7 ~ Construction of the Apron Expansion, Apron Culvert Replacement, Culvert Replacement and Access Restoration

During this period of construction there will be access to hangars 1, 2 and 3.

Phase 8 ~ Pulverization and Repaving of Apron

In this final phase drainage infrastructure will be completed. New aircraft tie-downs will be installed. The contractor will have 24 hours to put a final coat of asphalt  down on the whole ramp surface, in front of hangar 3 and entranceway to ramp. Fences, gates and disturbed areas will be restored.

The flight operations team will do everything possible to ensure flights and training proceed smoothly. We do not anticipate more than 2 and possibly 3 days of no flying possible. The closure period will depend on weather and on unexpected findings during construction.

Communications during the Construction

Communications with our staff, members and airport users will be a top priority. If you have questions or concerns, please contact the following people.

Private Aircraft Owners:

Dan Van Amelsvoort, Airport Manager [email protected] 905-838-1400 Ext. 215.

Nanci Soldo, Airport Administrator [email protected] 905-838-1400 Ext. 333

Flight Training Operations:

Judy Piccioni, Manager of Flight Training Administration and Services [email protected] 905-838-1400 Ext. 292